Local Government

Lake County Data Center Moratorium: Final Hearing December 1 on Extending the Pause to June 2027

At a final hearing on December 1, Lake County commissioners will weigh whether to resume accepting data center applications in unincorporated areas on December 13 or keep them on hold until June 11, 2027.

4 minute read

ShareFacebookX

Anyone with land outside Lake County’s cities and towns and plans to build a data center has had to wait since September. Under Ordinance 2026-43, the county stopped accepting data center applications in its unincorporated areas. On Tuesday, December 1, landowners could learn how much longer they will have to wait. At the second of two scheduled public hearings, the Board of County Commissioners will consider whether to let the suspension lapse or extend it another 180 days, to June 11, 2027.

The hearing will take place in Tavares, the county seat. Earlier coverage of the board, including the November 17 meeting at which the first hearing was scheduled, is collected in the Local Government archive. The extension remains a proposal. The details come from the county’s published ordinance notice and draft ordinance documents, checked today. This desk will report the December 1 outcome from the board’s posted minutes and actions.

What the extension would do

On its Proposed Ordinances page, the county lists the measure as the “Data Center Suspension Expansion Ordinance.” It would extend “the suspension of the acceptance of development applications for data centers, data center facilities, and data center utilities within unincorporated Lake County approved under Ordinance 2026-43 for an additional 180 days from December 13, 2026, to June 11, 2027.”

The county’s summary says the extension covers applications “for the construction or expansion of, and the issuance of building permits, development permits, development orders, or the rezoning of property for data center facilities within the unincorporated areas of Lake County.” Tavares, Leesburg, Clermont and the county’s other cities and towns govern projects within their own limits. The county’s ordinance page lists two public hearings, the first scheduled for the board’s regular meeting on November 17, 2026, and the second for December 1, 2026.

Why the county paused

The board adopted the suspension on September 8, 2026, according to a draft ordinance circulated in the Planning & Zoning Board’s October 7, 2026 packet. The draft gives the county’s reason. Lake County “currently lacks specific zoning provisions or development regulations addressing the unique operational characteristics, infrastructure requirements, and environmental considerations associated with data centers, data center facilities, and data center utilities.” The draft also says the county is in a region that “relies heavily upon groundwater resources from the Floridan Aquifer system, which has historically been subject to significant management and conservation.”

The draft would amend the Land Development Regulations to establish zoning districts and rules for certain types of data centers, with a conditional use permit required. It has yet to receive an ordinance number or an adoption date. The December 1 hearing concerns how much time the county will have to finish those rules while applications are suspended. If the board lets the suspension lapse, the county can resume accepting applications on December 13.

How to be heard on December 1

The county’s Board Meetings page lists Tuesday, December 1 as the board’s next regular meeting, ahead of December 15. The board meets in the Board Chambers at the Lake County Administration Building, 315 W. Main St., Tavares. Residents can use the public comment form for each meeting to submit comments in advance. The county says it shares comments submitted before 5 p.m. the day before a meeting with board members before they convene. Members receive comments submitted after 5 p.m. after the meeting. For questions about agenda items, the page lists the County Manager’s Office at 352-343-9888.

No individual data center is up for a vote, and the records this desk reviewed show no pending application. The choice before the board is whether to keep applications out for six more months or begin accepting them again while the rules for where the facilities can go are still in draft. This desk covers county tax and land-use decisions across the region, including Orange County’s adopted millage, and will report the December 1 vote when the Clerk publishes the board’s minutes and actions.

Featured image: Lake Harris at Leesburg, in Lake County. Photo: Ebyabe, CC BY-SA, via Wikimedia Commons.

Sources & notes

Every fact in this article was checked today against:

  • Lake County — “Lake County Ordinances” page, Proposed Ordinances section (lakecountyfl.gov) — the “Data Center Suspension Expansion Ordinance” listing: the two scheduled public hearings (11/17/2026 and 12/1/2026), the ordinance’s full title, and the county’s summary of its scope (extension of the Ordinance 2026-43 suspension of acceptance of applications for construction or expansion, and of issuance of building permits, development permits, development orders, or rezoning of property for data center facilities in unincorporated Lake County, for an additional 180 days from December 13, 2026, to June 11, 2027).
  • Lake County — draft ordinance, “Schedule of Uses – Data Centers” (Planning & Zoning Board staff reports, October 7, 2026 packet, c.lakecountyfl.gov) — the recital that on September 8, 2026, the Board adopted an ordinance suspending the acceptance of applications for data centers, data center facilities and data center utilities; the finding that the county lacks specific zoning provisions or development regulations addressing data centers’ operational characteristics, infrastructure requirements and environmental considerations; the Floridan Aquifer recital; and the draft’s purpose of establishing zoning districts and regulations for certain types of data centers with a conditional use permit required.
  • Lake County — Board Meetings page (lakecountyfl.gov) — Tuesday, December 1 listed first among upcoming meetings (ahead of December 15); the public comment form timing (before / after 5 p.m. on the day before a meeting); the County Manager’s Office phone number, 352-343-9888.
  • Lake County — Board of County Commissioners page (lakecountyfl.gov) — the board’s physical address, 315 W. Main St., Tavares, FL 32778.

This article reports a proposed ordinance and a scheduled public hearing. The November 17 first hearing is described only as scheduled, as the county’s ordinance page lists it; no vote count or outcome from November 17 is asserted, because the Clerk’s minutes and actions for that meeting have not been posted. The extension takes effect only if the board adopts it on December 1.

Filed under · · · ·

Editor’s Picks

  1. 1NewsEpic Universe Faces Its First Holiday Season
  2. 2ReviewsThe 10 Best Coffee Shops in Orlando
  3. 3TourismMagic Kingdom
  4. 4Top BusinessesHaan Coffee: Mills 50’s Korean-Inflected Roaster Tops Orlando Coffee
  5. 5ReviewsThe 10 Best Attractions & Things To Do in Orlando

Spotted an error? Tell us — corrections · How we rank

A. B. Newton

Orlando Citizen local government and taxes reporter. Covers the county commissions, Orlando City Council, property tax and budgets from agendas, adopted minutes and official releases — every figure traced to the document it came from.